|
Subscribe
|
Requirements and Time-Stamp
Your application time-stamp will be awarded at the end of the program launch based on the following approach:
Following program launch, applications will be prioritized according to the date and time the application is submitted, as described in the FIT Rules. Projects that are not offered a FIT contract at the end of the launch period will not be held to their reduced commercial operation date (COD) deadline. These projects will proceed to the economic connection test, FIT production line or FIT reserve as necessary to wait for the grid upgrades required to connect their projects. Once these project proponents are offered a contract, they will be subject to the commercial operation date deadlines set out in the FIT contract. Liquidated Damages If you are awarded a contract after submitting acceleration days, you will be subject to liquidated damages if you fail to achieve commercial operation within the time specified in your application.
All other contractual provisions, such as force majeure and event of default for being 18 months late in achieving commercial operation (six months for solar PV), remain in place. Example: A five-megawatt (MW) solar PV project might submit 30 COD acceleration days. This means that the new milestone date for commercial operation is the end of month 35, instead of the end of month 36. If the project is not able to meet the deadline and achieves commercial operation after 37 months (i.e., 60 days late), the applicant would be subject to liquidated damages of:
In addition, the contract term (payment period) is shortened by 60 days. A tie occurs where two applicants require the same connection resources and propose the same number of commercial operation date acceleration days.
|
Search
Key Documents
FIT Price Schedule
August 13, 2010 FIT Rules December 8, 2010 FIT Prescribed Forms August 11, 2010 FIT Multiple Project Guidelines August 4, 2010 FIT Contract December 8, 2010 Standard Definitions December 8, 2010 FIT Application Form Dec. 1, 2009 FIT Program Overview August 2010 Programme de TRG – Aperçu Août 2010 What's New
April 1, 2011
Bi-weekly FIT and microFIT Program reports March 18, 2011 Bi-weekly FIT and microFIT Program reports March 4, 2011 Bi-weekly FIT and microFIT Program reports February 24, 2011 Second Round of Large-Scale Renewable Energy Projects February 18, 2011 Bi-weekly FIT and microFIT Program reports February 9, 2011 Rule change for CAE FIT applications February 9, 2011 One-year extension of Milestone Date for Commercial Operation available for FIT contract holders February 4, 2011 Bi-weekly FIT and microFIT Program reports February 1, 2011 New FIT Program Proposed for Commercial Aggregators January 21, 2011 Bi-weekly FIT and microFIT Program reports January 5, 2011 Bi-weekly FIT and microFIT Program reports December 21, 2010 Priority ranking of first-round FIT projects posted December 8, 2010 Proposed FIT connection rule amendment Upcoming Events
|
|