Payments and Timelines
Text size:

The following table sets out key FIT contract payments and timelines. Please refer to the FIT contract for more details about these provisions.

 

FIT Contract On-shore wind Off-shore wind Solar PV
Waterpower Bioenergy
Milestone date for commercial operation three years four years three years five years three years
Notice to proceed response date 15 months 15 months 15 months 24 months 15 months
Notice to proceed daily delay amount $0.033/kW $0.067/kW $0.033/kW $0.067/kW $0.067/kW
Pre-construction liability limit

$400,000 +

$2.00/kW

$500,000 +

$2.00/kW

$250,000 +

$10.00/kW

$500,000 +

$20.00/kW

$400,000 +

$2.00/kW

First completion and performance security (initial security) $20/kW $20/kW $50/kW $20/kW $20/kW
Second completion and performance security (incremental NTP security) $10/kW $10/kW $25/kW $10/kW $10/kW

 
Note: Aboriginal and community projects have a lower security amount of $5/kW.

FIT - RC - Register
FIT - RC - Login
FIT - RC - Microfit
Search
Key Documents
FIT Price Schedule
August 13, 2010

FIT Rules
December 8, 2010

FIT Prescribed Forms
August 11, 2010

FIT Multiple Project Guidelines
August 4, 2010

FIT Contract

December 8, 2010

Standard Definitions
December 8, 2010

FIT Application Form
Dec. 1, 2009

FIT Program Overview 
August 2010

Programme de TRG – Aperçu
Août 2010


Upcoming Events